2026 Jan - Dec
Operation Mode
Several Bunch Modes
PDF :
Operation Calendar for printing (PDF)2026A
LEGEND :
     User Time  
     Shutdown  
  
  Machine Study / Beamline Study / Machine & Beamline Start-up Tuning / Beam Tuning 
NOTE :
User Time starts at 10:00 a.m. on the first day and ends at 10:00 a.m. on the last day of each operating period.
CONTACT :
 keikakuatspring8.or.jp
*The operation schedule in and after October 2025 is subject to change.

2026

カレンダ画像
 

Operation Modes

( Several Bunch Modes )

The operation mode changeover is scheduled to start at 10:00 am on the first day of each run and takes about 30 minutes to complete. The switched operation mode becomes available after the changeover.

Term
Run
Period
Operation Modes
(Current as of Feb. 2026)
2026A 1 10:00 Apr. 8 - 10:00 Apr. 14 B-mode
10:00 Apr. 14 - 10:00 Apr. 24 A-mode
10:00 Apr. 24 - 10:00 Apr. 30 B-mode
2 10:00 May 15 - 10:00 May 25 B-mode
10:00 May 26 - 10:00 Jun 8 H-mode
10:00 Jun 9 - 10:00 Jun 16 A-mode
10:00 Jun 16 - 10:00 Jun 22 D-mode
10:00 Jun 23 - 10:00 Jul. 3 C-mode
3 10:00 Jul. 9 - 10:00 Jul.15 C-mode
10:00 Jul.15 - 10:00 Jul. 21 A-mode
10:00 Jul. 21 - 10:00 Jul. 29  H-mode